The laboratory facility laid the foundation for the transition from groundbreaking innovations to commercially viable technology. Today it is used to run test series for industrial customers.
90%
Carbon Recovery
>95%
Electrical Efficiency

The pilot plant marked the step from proof of concept to proof of plant in an industrially relevant environment. It combines pre-conversion, plasma reforming, gas cleaning and automated control in a fully integrated system that produces on-spec syngas from real mixed waste and CO₂. Today, it is used to run extensive test campaigns, generating valuable data on the path to commercial-scale plants.
50 kW
Electrical Capacity
up to 10 kg/h
Waste

Cyclize designs, builds and operates a containerized plasma reforming pilot plant in Schwedt and runs a feedstock qualification programme in Stuttgart. The team leads process and plant design, plasma reformer development, automation and data analysis
Read more in the CASE study.
3,000 h
Operation Time
2026
Project Deployment

Cyclize is in preparation to kick-off planning and building a first-of-a-kind (FOAK) plant at industrial scale. The FOAK plant will be located in Germany and marks the first step of commercializing our technology.
2028
Project Deployment
300 kg/h
Waste Recycling Capacity
4,500 tons
CO₂ Recycled per Year

The first 10 MW industrial plant is Cyclize’s full-scale reference for continuous commercial operation. It translates the proven plasma process into a multi-line industrial facility. As the blueprint for subsequent plants across major chemical clusters, it is intended to demonstrate long-term reliability, on-spec syngas delivery and attractive unit economics at true commercial scale.
2031
Project Deployment
3,000 kg/h
Waste Recycling Capacity
70M m³/y
Syngas Production